To fight against flood risk (last event in August 2018 resulted in 42 persons evacuated, roads cuts, and houses inundated), the 2nd phase of Bizerte city flood protection project will start end September 2018 with a budget of 11 M Dinars (about 3.4 MEuros). A storm water network will be installed. Mr. Nejib Ben Chikha, Urban Hydraulic director from the Ministry of Equipment announced that the total cost of the project is 50 MDinars (about 15.5 MEuros)., including a completed 1st phase (3,5 MD)